Mulberry Cottages · Essex · 2026
Listed building consent and repair schedule for re-roofing a Grade II listed timber-framed building.
A failing peg-tile roof on an eighteenth century outbuilding to a former rectory at High Ongar. Heritage Unlimited prepared the Heritage Statement and roof details that secured listed building consent, then surveyed every exposed roof timber to discharge the condition on structural repairs.
Mulberry Cottages is a Grade II listed, two-storey timber-framed building at High Ongar, weatherboarded over a brick base beneath a steep hipped peg-tile roof with a catslide to the south. It was built in the eighteenth century as a coach house and service range to the neighbouring rectory, now Mulberry House, and has group value with that house and its stable.
An application for listed building consent to strip and re-lay the roof and add insulation was already with the council when the officer asked for a Heritage Statement written specifically for the roof works. We were brought in to provide it, working with the planning consultants, Smart Planning. Consent was granted by Epping Forest District Council in November 2025, and the details required by condition were approved in March 2026.
- Property
- Mulberry Cottages, Chelmsford Road, High Ongar
- Listing
- Grade II
- Location
- High Ongar, Essex
- Authority
- Epping Forest District Council
- Service
- Listed Building Survey and Repair AdviceHeritage StatementListed Building Survey and Repair Advice, Heritage Statement
- Year
- 2025 to 2026
- Outcome
- Listed building consent granted; repair details approved
Insulating a peg-tile roof without changing how it looks.
We inspected the building and its roof void in September 2025, with a laser survey of the void carried out the same day. The roof showed several phases of earlier repair, with inconsistent counter-battening and residual straw beneath the tiles, and fewer than one in five of the tiles was expected to be fit for reuse.
The owners wanted to insulate. Non-breathable modern insulation is rarely acceptable on a historic timber roof, so we worked up an over-rafter detail using a breathable insulated membrane, counter-battened and unvented so that no tile vents were needed, with the eaves and gable detail unchanged. The ridge rises by no more than 28mm. Sound historic tiles were to be gathered on one hip, with matching handmade clay tiles on the main slopes.
Listed building roof repair: consent granted on the statement and the drawings.
The Heritage Statement drew on the county map of 1777, the tithe map and apportionment of 1848 and Ordnance Survey editions from 1881, and assessed the building and the setting of its two listed neighbours. It concluded that the works would cause no harm.
Listed building consent (EPF/1643/25) was granted on 10 November 2025. The officer’s report records that the assessment relied on the Heritage Statement and drawings, which were considered sufficient, and that the change in ridge height would be barely perceptible. Our roof detail drawings are named among the approved documents.
Every rafter numbered, tested and scheduled.
The consent required a survey of the roof frame, a schedule of works and a method statement before any structural repair. With the roof stripped under a temporary cover in February 2026, we numbered each rafter on the survey drawings, inspected and probe-tested each one, and measured and photographed every defect.
The frame was in reasonable condition for its age, with localised failures: the main ridge decayed for most of its length, failed hip ridges and a failed purlin to the catslide, and decay to the wall plates. The repair approach was to splice new timber to old with traditional scarf and half-lap joints, replacing a member in full only where too little sound timber remained, and to keep dropped rafters in place with new rafters alongside so that the repair can be read as modern work.
The schedule of timber repairs, survey drawings, photographic record and method statement were submitted on 5 March 2026 and approved (EPF/0476/26) on 13 March 2026.
What we did
Two services, one outcome.
Listed Building Survey and Repair Advice
We surveyed the roof timber by timber and produced the repair schedule, drawings and method statement that discharged the condition.
About Survey and Repair Advice →Heritage Statements
The Heritage Statement and roof detail drawings supported the listed building consent application for re-roofing and insulation.
About Heritage Statements →Historic roof in need of repair?
Tell us about your project.
We survey listed buildings and prepare repair schedules and consent applications across England and Wales. Send us the details and you will have a response within one working day.
To get a fast outline approach, share:
- The address of the property and its grading, if known
- A short description of the proposed works
- Where you are in the planning process
- Your role: owner, developer, architect, or public body