Bridgemaster’s House, Tower Bridge · London · 2026
Heritage Statement for the Grade II listed Bridgemaster’s House at Tower Bridge.
The refurbishment of the offices of the team that operates Tower Bridge, in a listed house of 1906 on the bridge approach. Heritage Unlimited’s Heritage Statement showed that the one solid wall affected belonged to a 2013 extension, and listed building consent was granted with a finding of no harm.
Bridgemaster’s House stands on the west side of the southern approach to Tower Bridge. It is dated 1906 and was designed by Sydney Perks as a house for the Bridge Master and his deputy. It is built of red brick over a ground floor faced in Portland stone, with a stone frieze, cornice and banded quoins to the street.
It is listed Grade II, stands in Tower Bridge Conservation Area beside the Grade I listed bridge, and lies within the local setting of the Tower of London World Heritage Site. It is still used for its original purpose in a modern form, as offices for the team that operates the bridge. A four-storey extension was added at the rear under consents granted in 2013. We inspected the building in July 2026 and prepared the Heritage Statement that month. Southwark Council granted listed building consent in September 2026.
- Property
- Bridgemaster’s House, Tower Bridge Road, London
- Listing
- Grade II; Tower Bridge Conservation Area
- Location
- Tower Bridge, London
- Authority
- London Borough of Southwark
- Year
- 2026
- Outcome
- Listed building consent granted
Office works in a listed building.
The offices needed refurbishing and rearranging on every floor: partitions taken out and put in, new doors and glazed screens, WCs and tea points, and one new opening through a section of solid wall on the ground floor. Nothing was proposed to the outside of the building.
Works of that kind need listed building consent wherever they would affect the character of a listed building, and a rear extension that is attached to a listed building is part of it in law, however recent. Under s.16(2) of the Planning (Listed Buildings and Conservation Areas) Act 1990 the council must have special regard to the desirability of preserving the building and any features of special interest it possesses.
To apply that test the council needs to know which fabric dates from 1906 and which is modern. On most of the scheme the answer was plain. On the solid wall it was not.
Reading the building against its own records.
We inspected the building inside and out in July 2026. We traced the site on Ordnance Survey maps from the 1870s to 1970 and on aerial photographs of 1922 and 1934, and went through the planning history, including the drawings approved for the 2013 extension.
Inside, almost everything visible proved to be modern stud partitioning and plasterboard. The survivals from 1906 were few and easy to list: a fireplace surround on the second floor, a run of brick arches at the lower level and a small area of exposed original brickwork. The staircase is modern.
The solid wall was settled from the 2013 drawings. Setting the present ground floor plan against them showed that the section of wall affected lies within the 2013 extension and is not part of the house of 1906.
The Heritage Statement.
Our Heritage Statement of July 2026 described the house and its significance, which lies in its connection with the working of Tower Bridge, its design by Perks and its well-preserved street front. It set out the map, photographic and planning evidence, went through the proposals floor by floor, and identified the ground floor opening as the one element needing closer assessment.
It concluded that the works were confined to modern fabric, that they would cause no harm to the listed building, and that with no external change the setting of Tower Bridge and the other listed buildings nearby would be unaffected.
Consent granted.
Southwark Council granted listed building consent in September 2026. No objections were received. The officer’s report reaches the same finding on the wall, on the same evidence: a review of the layout against the plans approved in 2013 “shows that the wall was built as part of the 2013 rear extension rather than the original 1906 building”.
It concludes that “No harm has been identified to the significance of Bridgemasters House”. The officer visited in September and confirmed that the works were confined to modern fabric. The consent carries only the standard conditions.
What we did
Two services, one outcome.
Heritage Statements
A Heritage Statement that used the building’s own planning record to show that the one solid wall affected was part of a 2013 extension and not the house of 1906.
About Heritage Statements →Listed Building Consent
We advised on the route to take and recommended a single application for listed building consent covering every element of the works.
About Listed Building Consent →Internal works to a listed building?
Tell us about your project.
We prepare heritage statements for refurbishment and internal alterations at listed buildings across England and Wales. Send us the details and you will have a response within one working day.
To get a fast outline approach, share:
- The address of the property and its grading, if known
- A short description of the proposed works
- Where you are in the planning process
- Your role: owner, developer, architect, or public body