Nos. 40-48 High Street · Theale · 2022 to 2024

Heritage Assessment for a range of high street properties.

Heritage Unlimited advised on this range of high street properties in Theale from 2022 to 2024: a Heritage Assessment and Addendum for pre-application advice on the whole row, then Heritage Statements for the conversion of Nos. 44 and 46, granted planning permission in September 2024, and for a new house in the garden behind the listed building.

ListingGrade II

Modern shopping practices and way of life has resulted in the decline of the English high street, which in turn has resulted in the character of the traditional retail and commercial high street being changed.

Premises have become vacant as businesses, often decades and sometimes century old local and national retail companies, have become unsustainable and no longer able to compete with the lower priced and the convenience of internet shopping. This combined with new working practices resulting from the global pandemic have also contributed to changing the character of the high street. In April 2023, Heritage Unlimited were appointed by the client to provide a Heritage Assessment for a range of properties on the High Street in Theale to support a pre-application submission to help inform and guide adaptations and reuse of these properties for a viable and sustainable future, thereby positively contributing to the character of the historic high street. These properties comprised a grade II listed building (nos. 46a and 48), the non-designated heritage assets (NDHA) of nos. 44 and 46, and the undesignated nos. 40, 40a and 42, all within the Theale High Street Conservation Area.

At a glance
Property
Nos. 40-48 High Street
Listing
Grade II, NDHA, Conservation Area
Location
Theale
Authority
West Berkshire Council
Year
2022 to 2024
Outcome
Planning permission granted for Nos. 44 and 46, September 2024

Vacant High Street Properties in a Historic Linear Streetscape.

Some of the units were vacant and fallen into a partial state of disrepair, a few were in commercial use and one was a residential dwelling. Nos. 44 to 48 were entirely vacant, the small shop at no. 46a having traded as a newsagent until 2020, while the ground floors of nos. 40, 40a and 42 were still in use and only their upper floor offices stood empty.

The historic linear high street is characterised by traditionally constructed properties using vernacular materials, brick, tile and timber-framing.

HUL already knew nos. 44 and 46. In 2022, after the council identified the pair as non-designated heritage assets during an earlier planning application, HUL advised the owner and the architect on which works needed planning permission, set out the likely sequence of construction, which showed that the cottages began as a single house entered beside its central chimney, and mapped the pre-1948 building line that defined the permitted development rights. A certificate of lawfulness for a ground floor extension and the removal of internal walls followed in January 2023. For the 2023 instruction, HUL carried out desk-based research for each property as well as a site inspection of the buildings’ external and internal fabric in order to understand the historic and current context of each building and also as a group.

Creative and Adaptive Reuse of Heritage Assets.

It was considered that the process presented an invaluable opportunity to reuse the historic properties creatively and adaptively, and any proposed conversion and/or reconfiguration and refurbishment would aid their longevity and could even constitute an enhancement to the historic character of the high street.

A proposed residential conversion would also provide some public benefit in the creation of additional housing in the area and removing the risk of further deterioration of vacant buildings by their adaptation and reuse.

HUL produced a Heritage Assessment to aid pre-application submission, issued in June 2023. The document provides the conservation officer sufficient and necessary information to give them an understanding of the heritage assets’ story and how this in turn guides future changes so the building can continue to positively contribute to the streetscape.

From Pre-Application to Planning Permission.

In October 2023 the scheme grew to include a detached 1.5 storey building in the garden behind the listed building, and HUL issued a Heritage Assessment Addendum assessing it within the setting of nos. 46a and 48 and the conservation area. The same month HUL met the council’s planning officer on site to discuss the proposals for the whole row.

The council’s pre-application response followed in February 2024 and was positive overall. We were subsequently engaged to provide a Heritage Statement to support a planning application for the extension and conversion of nos. 44-46 High Street, a non-designated heritage asset, into two flats, issued in March 2024. The council’s conservation officer found that it “appropriately describes the significance of the affected heritage assets”, and once the plans had been amended to retain the central chimney stack, planning permission was granted in September 2024.

HUL used their specialist knowledge of the planning system relating to heritage assets within a team of professionals providing their own specialism to guide the client on changes that would be acceptable and achievable to their heritage assets which varied in designation but all encompassed by the conservation area.

A New House in the Garden of the Listed Building.

In September 2024 HUL issued a Heritage Statement for a detached 1.5 storey, three bedroom house on land to the rear of nos. 46a and 48, within the setting of the listed building and the conservation area. The design had been revised in response to the conservation officer’s pre-application advice, with red brick, segmental arched openings and a half-hipped clay tile roof drawn from the front of nos. 44 and 46, and the statement concluded that it would preserve the setting of the listed building and the character and appearance of the conservation area.

The application for the new house was submitted in October 2024 and was withdrawn in January 2025.

Nos. 40-48 High Street elevation
Nos. 40-48 High Street, Theale: the range of properties within the conservation area.
Nos. 40-48 High Street detail
The historic linear streetscape characterised by vernacular materials including brick, tile and timber-framing.
Nos. 40-48 High Street morphology
Historic mapping and morphology analysis informing the Heritage Assessment.
Nos. 40-48 High Street site plan
Site context showing the Grade II listed building, non-designated heritage assets and undesignated buildings within the conservation area.

Services on this project

Heritage consultancy services used at Nos. 40-48 High Street.

Lead service

Heritage Assessments

A Heritage Assessment in June 2023 and an Addendum in October 2023 supported pre-application advice on the whole row, a grade II listed building, a pair of non-designated heritage assets and three unlisted buildings in the conservation area, setting out what matters in each and how they could be reused.

About Heritage Assessments →
Supporting service

Heritage Statements

A Heritage Statement for the extension and conversion of nos. 44 and 46 into two flats supported the planning permission granted in September 2024, and a second assessed a new house in the garden behind the listed building.

About Heritage Statements →
Supporting service

Development Advice

From 2022 we advised on which works to nos. 44 and 46 needed planning permission, met the council on site at the pre-application stage and commented on its pre-application response.

About Development Advice →

Considering the reuse of a heritage asset?

Tell us about your project.

We are available for Heritage Statement commissions, heritage assessments and conservation advice across England and Wales. Send us the details and you will have a response within one working day.

What to send

To get a fast outline approach, share:

  • The address of the property and its grading, if known
  • A short description of the proposed works
  • Where you are in the planning process
  • Your role: owner, developer, architect, or public body